Daily Production Record

Daily Production Record

This screen is used to submit your Daily Production record. Please fill out this form once a day after completing any pile records or equivalent form.

DPR

To fill out the form please enter the following information:

  • Operator Name: enter the name of the rig Opperator. This will usually be your own name.
  • Date: Click in the date field and select the date from the calendar. This will usually be today.
  • Project ID: Enter the project ID. This is the same as the project ID on the pile record. Start typing and job number suggestions will appear. Either select one, or ensure that the number you eneter has appeared and turned green.
  • Rig: Select a rig from the list. If the rig you are using is not in the list, please contact the job engineer.
  • Installed Piles: Please enter the number of piles installed during the selected day. Whole numbers only.
  • Pitched Metres: Please enter the number of metres pitched during the selected day. Up to two decimal places.
  • Driven Metres: Please enter the number of metres driven during the selected day. Up to two decimal places.
  • Recoverabled Delay: Please enter the number of hours of recoverable delay during the selected day. Up to two decimal places. Enter 0 if none.
  • Recoverable Delay Reason: Please enter the reason for the recoverable delay. Leave blank if none.
  • Non-Recoverable Delay: Please enter the number of hours of non-recoverable delay during the selected day. Up to two decimal places. Enter 0 if none.
  • Non-Recoverable Delay Reason: Please enter the reason for the non-recoverable delay. Leave blank if none.
  • Breakdown: Please enter the number of hours of breakdown during the selected day. Up to two decimal places. Enter 0 if none.
  • Preventative Maintenance: Please enter the number of hours of preventative maintenance during the selected day. Up to two decimal places. Enter 0 if none.
  • Hired Rig Breakdown: If the rig is hired, please enter the breakdown here instead. Up to two decimal places. Enter 0 if none.
  • Breakdown Reason: Please select the breakdown reason from the list. If the reason is not in the list, please contact the job engineer. Leave blank if there is no breakdown.

Once you have filled out the form, click the submit button. If the form is invalid, fields with errors will be highlighted in red. Please correct these errors and try again. If there are no errors, please click the submit button again and you will be presented with a box to sign the record.

DPR Signature

Please sign the record with your finger and then click Save Signature. The submission process is now complete.